Question: Question 3 . ( 3 0 points ) ABC computer Co . Ltd . is designing an assembly line to produce 1 9 6 keyboards

Question 3.(30 points)
ABC computer Co. Ltd. is designing an assembly line to produce 196 keyboards per an 8 hr shift. The following table identifies the work elements, times, and immediate predecessors.
\begin{tabular}{|c|c|c|}
\hline Task & Task time (sec) & Preceding tasks \\
\hline A & 40 & None \\
\hline B & 80 & A \\
\hline C & 30 & D, E, F \\
\hline D & 120 & B \\
\hline E & 15 & B \\
\hline F & 20 & B \\
\hline G & 25 & A \\
\hline H & 145 & G \\
\hline I & 130 & H \\
\hline J & 115 & C, I \\
\hline
\end{tabular}
1) Find an optimum layout in the sequence of workstations where every work element is assigned in a workstation. Provide the sequence of workstations by indicating WS1, WS2, WS3...., with tasks clearly. (20 points)
1) Find efficiency of the optimum layout. (10 points)
 Question 3.(30 points) ABC computer Co. Ltd. is designing an assembly

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!