Question: Question 3 3 . 1 The project network is the tool used for planning, scheduling, and monitoring project progress. The network is developed from the
Question
The project network is the tool used for planning, scheduling, and monitoring project progress. The network is developed from the information collected for the WBS and is a graphic flow chart of the project job plan. The network depicts the project activities that must be completed, the logical sequences, the interdependencies of the activities to be completed, and in most cases the times for the activities to start and finish along with the longest paths through the networkthe critical path. The network is the framework for the project information system that will be used by the project managers to make decisions concerning project time, cost, and performance.
Khutso construction has recently signed a contract to build a garage for the Maibelas. The table below shows the tasks, predecessors and time for the project. Construct a project network.
begintabularllcc
hline ID & Description & Predecessor & Time days
hline A & Prepare site & None &
B & Pour foundation & B &
C & Erect frame & C &
D & Roof & C &
E & Windows & C &
& Doors & C &
G & Electrical & D E F G &
H & Roughin frame & F G &
I & Door opener & HI &
J & Paint & J &
K & Cleanup & &
hline
endtabular
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock