Question: QUESTION 3 4 points Save Answer Consider the tasks, durations, and predecessor relationships in the following network. Draw the network. This can be done in

QUESTION 3 4 points Save Answer Consider the tasks, durations, and predecessor relationships in the following network. Draw the network. This can be done in Word, Excel, or by hand and saved as a pdf or image. Activity Immediate Optimistic Most Likely Pessimistic Predecessors) (Weeks) (Weeks) (Weeks) A 4 10 A 8 20 A 12 16 B ON 3 D. C 6 8 22 C 4 F . CO N W 2 ANN F 10 . E, G, H 12 N w Attach File