Question: Question 3 !40/0! It is required to construct a small coffee shop. The contractor was asked to study the possibility of completing the work earlier.

 Question 3 !40/0! It is required to construct a small coffee

Question 3 !40/0! It is required to construct a small coffee shop. The contractor was asked to study the possibility of completing the work earlier. The table below lists the activities involved in building the coffee shop with the associated normal and crash cost. Calculate the normal cost, the least-cost, and crash duration for the project below. Calculate the cost associated with each duration. Indirect cost (overhead) is $100 per day. Duration Cost 5 Act IPA Normal Crash Normal Crash A - 7 5 500 640 B A 6 5 550 630 C A 8 5 800 935 D B 10 7 1200 1440 E B,C 6 4 600 700 F C 4 3 500 590 G D,F 4 2 700 1000 H E,F 7 4 650 950 | G,H 2 2 300 300

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!