Question: Question 3 5 points Save Answ We have a project where Cost Performance Indicator (CPI) of.80 which means we are spending more money than we

Question 3 5 points Save Answ We have a project

Question 3 5 points Save Answ We have a project where Cost Performance Indicator (CPI) of.80 which means we are spending more money than we should spend. And we have Schedule Performance Indicator (SPI) of 1.20, which means we are ahead of schedule. Do you think we should be worried because we are spending more than budgeted money? Explain your answer (in your own words). 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer