Question: Question 3 7 4 pts An activity has an optimistic time estimate of 4 days, a most likely time of 6 days, and a pessimistic

Question 37
4 pts
An activity has an optimistic time estimate of 4 days, a most likely time of 6 days, and a pessimistic time estimate of 10 days. Its expected time is approximately
4 days
6.3 days
6 days
10 days