Question: 1.1 What is the projects expected duration? What is the standard deviation of each activity? 1.2 Estimate the probability of finishing the project in 28

1.1 What is the projects expected duration? What is the standard deviation of each activity?

1.2 Estimate the probability of finishing the project in 28 days or less.

1.3 You learn you can receive a significant bonus if the project finishes on day 25. What is the probability of this occurring?

1.4 To provide your top managers with a 95% assurance of finishing on time, how long should the projects duration be?

Activity Immediate Predecessor Optimistic Time Estimate (a) Most Likely Time Estimate (m) Pessimistic Time Estimate (b)
A none 2 5 8
B A 5 6 10
C A 2 4 6
D B, C 4 7 15
E D 3 4 8
F C 2 3 6
G F 4 5 9
H E, G 1 2 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!