It is estimated that a federally funded work package will require 80 man hours to complete. The laborers for this work package all have a Davis Bacon wage rate of $15.88 with no fringes required. The burdened wage rate for these workers is $41.37 and is based on the Davis Bacon rate. Calculate the cost of the labor for this work package.
about $3310
about $1270
about $4580
about $2040