Question: Question 3 9 ( 1 point ) It is estimated that a federally funded work package will require 8 0 man hours to complete. The
Question point
It is estimated that a federally funded work package will require man hours to complete. The laborers for this work package all have a Davis Bacon wage rate of $ with no fringes required. The burdened wage rate for these workers is $ and is based on the Davis Bacon rate. Calculate the cost of the labor for this work package.
about $
about $
about $
about $