Question: Question 3 9 3 Points A project manager is trying to complete a software development project but cannot get enough attention for the project. Resources

Question 39
3 Points
A project manager is trying to complete a software development project but cannot get enough attention for the project. Resources are focused on completing process-related work, and the project manager has little authority to properly assign resources. What form of organization must the project manager be working in?
Functional
Matrix
Expediter
Expediter