Question: Question 3: (9 marks) The following work breakdown table displays the tasks in a particular project. Construct a network diagram using the information in the
Question 3: (9 marks)
The following work breakdown table displays the tasks in a particular project.
- Construct a network diagram using the information in the table;
- Identify the critical path;
- Calculate the planned duration of the project in days;
- Calculate the total float of the project in days.
| Activity ID | Duration In days | Immediate Predecessor |
| A | 5 | None |
| B | 4 | A |
| C | 3 | A |
| D | 6 | B, C |
| E | 4 | B |
| F | 2 | D, E |