Question: Question 3: (9 marks) The following work breakdown table displays the tasks in a particular project. Construct a network diagram using the information in the

Question 3: (9 marks)

The following work breakdown table displays the tasks in a particular project.

  1. Construct a network diagram using the information in the table;
  2. Identify the critical path;
  3. Calculate the planned duration of the project in days;
  4. Calculate the total float of the project in days.

Activity

ID

Duration

In days

Immediate

Predecessor

A

5

None

B

4

A

C

3

A

D

6

B, C

E

4

B

F

2

D, E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!