Question: Question 3: 11 marksj The following work breakdown table displays the tasks involved in a particular project. a) Construct a network diagram using the information

Question 3: 11 marksj The following work breakdown table displays the tasks involved in a particular project. a) Construct a network diagram using the information in the table (8 marks); b) Identify the critical path (1 mark); c) Calculate the planned duration of the project in days {1 mark); d) Calculate the total float of the project in days (1 mark). Immediate Predecessor