Question: QUESTION 3 Assume that your capstone project is broken down into a number of major jobs or activities, as shown in Table below: Activity Description
QUESTION 3 Assume that your capstone project is broken down into a number of major jobs or activities, as shown in Table below: Activity Description Activity Identification Immediate Predecessor Activity Activity Duration (Days) Proposal defense A 5 Problem Statement B 4 Objectives C A 3 Literature review D A 4 Methodology E A 6 Results F B, C 4 Discussion and analysis G D 5 Recommendation H D, E 6 Challenges I F 6 Conclusion J G, H 4 a. Draw a Gantt chart. b. Develop a CPM network. c. Determine both the critical path of the network and the project duration period
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts