Question: QUESTION 3 Ayra Software Sdn Bhd is a software company located in Damansara, Malaysia. One of the project that is being planned has the following

QUESTION 3

Ayra Software Sdn Bhd is a software company located in Damansara, Malaysia. One of the project that is being planned has the following activities:

Task

Identifier

Activity

Predecessor Activity

Duration (days)

Developer

A

Establish project

-

2

2

B

Establish customer requirements

-

2

2

C

Product software specification documents

A

3

2

D

Write test plans

B

2

2

E

Write code

C,D

3

1

F

Developer testing

C,D

2

1

G

Implementation

E,F

1

2

H

Write manuals

G

1

1

Table 1 Project Activities

a) For each of the activities, design the Early Start (ES), Late Start (LS), Early Finish (EF) and Late Finish (LF) Time, as well as Total Float (FL) days. Determine the critical path(s).

(10 marks)

b) Using the resources columns in Table 1, produce the resource plan in the form of resource chart. The maximum number of developer is 3 pax. Take note of the developer availability. The additional days should not exceed 7 days and the last day should end with H.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!