Question: QUESTION 3: C. Two jobs must be processed through a five-machine shop. The processing times are shown below. The routing of the jobs are as

QUESTION 3: C. Two jobs must be processed through

QUESTION 3: C. Two jobs must be processed through a five-machine shop. The processing times are shown below. The routing of the jobs are as follows: J M4, M5, M, M2, M2 J2 M5, M4, M, M3, M2 Machine Job M M M3 M4 M5 J 4 4 8 6 J 2 5 7 4 3 a) (20 points) Using the graphical approach, find the minimum makespan schedule, and interpret it. What is the value of Cmax? (Solving by other methods will not be evaluated!) b) (5 points) Calculate the total waiting times of J and J2