Question: Question 3. Consider the following activity information for a project and solve the below questions: Activity Predecessor Normal Crash Normal cost Crash Cost time Time

Question 3. Consider the following activity

Question 3. Consider the following activity information for a project and solve the below questions: Activity Predecessor Normal Crash Normal cost Crash Cost time Time (total) (days) (days) 5 1000 4 A 1400 3 B 3 800 A,B 900 3 1 600 2000 1600 4 B 2 1200 800 C,D 3 5 1650 1300 1 3 E F 1. The crash cost per day 2. Find the total normal schedule and cost 3. Which activities should be crashed to reduce a project deadline as much as possible, and provide additional cost of crashing. CDEE