Question: Please Answer! Thanks!!! (6 points) Problem 3: Given the following. 2 B 7 3 E 1 4 5 D 2 6 3 3 Crash Crashed

Please Answer! Thanks!!!

Please Answer! Thanks!!! (6 points) Problem 3:

(6 points) Problem 3: Given the following. 2 B 7 3 E 1 4 5 D 2 6 3 3 Crash Crashed Normal Time Cost Time Normal Activity (days) (total) (days) Cost A: Obtain 4 $800 7 $500 instructor B: Locate a room 2 350 3 200 C: Check costs 4 900 6 500 D: Room open? 1 500 3 200 E: Schedule class 1 _550 2 300 $3100 1. Find the crash cost per day. 2. Which activities should be crashed to meet a project deadline of 10 days with a minimum cost? Assume partial crashing. 3. What is the new cost after crashing