Question: Question 3: Develop resource constraint schedule for this project based on the critical path identified in Question 2 and the resource limitation of maximum 4
Question 3: Develop resource constraint schedule for this project based on the critical path identified in Question 2 and the resource limitation of maximum 4 persons working at a time in this project
Activity | Duration (Days) | Resource Requirements | Dependency |
|---|---|---|---|
Initial informational meetings | 5 | 2 | - |
Community mailing about construction project | 3 | 2 | - |
Marketing Workshops | 5 | 3 | Initial informational meetings |
Medical Center volunteer Workshop | 4 | 3 | Community mailing about construction project |
Create Community groups | 5 | 2 | - |
Medical Center staff Workshop | 5 | 3 | Initial informational meetings |
Presentation prepared for Speaker's Bureau | 4 | 2 | Marketing Workshops, Create Community groups |
Provide updates to community | 5 | 3 | Presentation prepared for Speaker's Bureau |
Inquiry log established | 5 | 1 | Create Community groups, Medical Center staff Workshop |
Ground-breaking ceremony | 12 | 4 | Provide updates to community |
Marketing plan developed | 7 | 3 | Inquiry log established |
PR firm contracted | 5 | 2 | Inquiry log established, Marketing plan developed |
Hire Marketing Director | 12 | 2 | PR firm contracted, Marketing plan developed |