Question: Question 3 ( Fall 2 0 2 1 , Exam 1 ) The number of visitors to Grand Canyon is forecasted using Double Exponential Smoothing

Question 3(Fall 2021, Exam 1) The number of visitors to Grand Canyon is forecasted using Double Exponential Smoothing (DES), with intercept and slope at the end of January (month 1) given as, S1=2,000 and G1=300.
Assume that alpha =0.2 and beta =0.1 for all calculations.
(a) What is the one-step ahead forecast made in January for February?
FJan,Feb=
(b) What is the multi-step ahead forecast made in January for April?
FJan,April=