Question: Question 3 For the project below: a. Construct an AON diagram. (5 Marks) b. Construct a CPM network representation. (5 Marks) c. Determine the ES,

Question 3 For the project below: a. Construct an

Question 3 For the project below: a. Construct an AON diagram. (5 Marks) b. Construct a CPM network representation. (5 Marks) c. Determine the ES, EF, LS, and LF times for the project. (15 Marks) d. What is the critical path? (5 Marks) Crash Normal Additional cost to crash Activity Duration Predecessor Duration an activity (cost/week) (weeks) 1 1 1 2 3 2 2,000 1 3 2 1 3,000 2 4 4 3 1,000 2 5 1 500 3,4 N 6 1 1 5 7 4 3 2,500 5 8 3 2 5000 6,7 9 2 1 500 2 10 1 1 8,9

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!