Question: Question 3 Given the manufacturing line setup below, please indicate what changes are necessary to create a balanced line, explain your reasoning. Given the manufacturing
Question 3
Given the manufacturing line setup below, please indicate what changes are necessary to create a balanced line, explain your reasoning.
Given the manufacturing line setup below, please indicate what changes are necessary to create a balanced line, explain your reasoning. Process Time 80 70 60 50 ( 40 50 30 30 20 15 30 10 10 10 10 0 Station 1 Station 4 Station 2 Station 3 Manufacturing Station Location Process A Process B Process Process -Takt Process Time 1.2 1 08 Time (min) 0.6 0.4 0 Station 1 Station 2 Station 3 Station 4 Manufacturing Station Location Process A Process Process Process D -TaktStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts