Question: Question 3 Given the planned resource utilization chart as shown in Figure 3 . And Precedence task in Table 6 Table 6 table [
Question Given the planned resource utilization chart as shown in Figure And Precedence task in Table
Table
tableTaskPredecessor,DayABCDCEF
tableCarpenterDass,SlackTask A CarpenterTask CarpenterTask C GrpenterTask D CarpenterTask E CarpenterTask F CarpenterDayCarpenter
Figure
a Fill in Figure the cell in bold Examine the number of carpenters that are needed each day based on the earliest start and finish times for each activity. And examine the number carpente days that are needed for each task. : mark
b Draw the Resource Profile for the Carpenter. : marks