Question: QUESTION 3 Given the Product Structure Tree shown above, you need to satisfy a demand of 50 units of Final Product A to be delivered

QUESTION 3

  1. QUESTION 3 Given the Product Structure Tree shown Given the Product Structure Tree shown above, you need to satisfy a demand of 50 units of Final Product A to be delivered in Week 7, when and how many of component E are required to prepare assuming you don't have any on-hand inventory or scheduled receipts coming. Number in the bracket is the quantity required to produce the next upper level item.

    A.

    150 units in Week 1 and 200 units in Week 2

    B.

    200 units in Week 1

    C.

    100 units in Week 1 and 50 units in Week 2

    D.

    200 units in Week 1 and 150 units in Week 2

Final Product A Lead Time: 2 Weeks Subassembly B (2) Lead Time: 2 Weeks Subassembly C (3) Lead Time: 1 Week Component D (3) Lead Time: 3 Weeks Component E (2) Lead Time: 2 Weeks Component E (1) Lead Time: 2 Weeks Component F (2) Lead Time: 2 Weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!