Question: QUESTION 3 Planned value ( PV ) is simply R 5 5 3 0 0 . To calculate the planned value ( PV ) we
QUESTION
Planned value PV is simply R To calculate the planned value PV we need
to multiply the earned value EV by the percentage of the project that is complete of
If the actual cost AC is R how would you determine the following?
a The earned value EV
b The cost variance of that month.
c Cost performance index
d Discuss the outcome of your calculated cost performance index to give us what
does it tells the stakeholders.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
