Question: Question 3: Sequence the jobs shown below by using a Gantt chart. Sequence the jobs in priority order 1, 2, 3, 4. Job Work Center/Machine

Question 3:

Sequence the jobs shown below by using a Gantt chart. Sequence the jobs in priority order 1, 2, 3, 4.

Job Work Center/Machine Hours Due Date (days)

1

A/3, B/2, C/2

3

2

C/2, A/4

2

3

B/6, A/1, C/3

4

4

C/4, A/1, B/2

3

  1. When is each job delivered? (Marks 0.5)
  2. Which department is the bottleneck? (Marks 0.5)
  3. Calculate the machine utilization? (Marks 0.5)