Question: Question 3 - Short Term Scheduling 25 Marks Five architectural rendering jobs are waiting to be assigned at the Urban Development Corporation (UDC). Their work

Question 3 - Short Term Scheduling 25 Marks Five
Question 3 - Short Term Scheduling 25 Marks Five architectural rendering jobs are waiting to be assigned at the Urban Development Corporation (UDC). Their work processing times and due dates are given in the following table. The Corporation wants to determine the sequence of processing according to FCFS rule. Jobs were assigned a letter in the order they arrived. Today is day 1, and work begins today. Job A B D E Job work Processing Time (days) 6 2 8 3 9 Job due date (days) 8 6 18 15 23