Question: Question 3 Table 7 . 1 4 You are responsible for managing a project with the following a ctivities ( times are given in weeks
Question
Table
You are responsible for managing a project with the following a ctivities times are given in weeks
tableTaskPredecessor,Optimistic,Most Likely,PessimisticABACBDED
Using Table which activity has the largest standard deviation, and how lage istrat sanderd devition?
Activity: ; weeks
Activity B; weeks
Activity D; weeks
Activity C; weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
