Question: Question 3 Table 7 . 1 4 You are responsible for managing a project with the following a ctivities ( times are given in weeks

Question 3
Table 7.14
You are responsible for managing a project with the following a ctivities (times are given in weeks),
\table[[Task,Predecessor,Optimistic,Most Likely,Pessimistic],[A,.-,5,8,10],[B,A,7,10,12],[C,B,8,10,14],[D,.-,11,15,20],[E,D,12,14,18]]
Using Table 7.14, which activity has the largest standard deviation, and how lage istrat sanderd devition?
Activity: A;0.83 weeks
Activity B; 1.25 weeks
Activity D; 1.5 weeks
Activity C; 1.25 weeks