Question: QUESTION 3 Table Q3 shows the activities involve in building a shop, with activity times in weeks. Table Q3 Time (weeks) > Activity A B

QUESTION 3 Table Q3 shows the activities involve

QUESTION 3 Table Q3 shows the activities involve in building a shop, with activity times in weeks. Table Q3 Time (weeks) > Activity A B D E F G H Predecessor 5 8 3 4 5 7 6 8 6 5 A B A D,E F G HI J a) Draw the precedence diagram. b) List all the paths. c) Calculate the ES, EF, LS, LF and slack for activity B, C, F and H. List your answer in the table. d) Determine the total weeks required to complete the project and identify the critical path. (10 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!