Question: QUESTION 3 The scoring models used by two transport project managers, Len and Lerato, selecting suitable transport projects, vary from being very basic to very

QUESTION 3
The scoring models used by two transport project managers, Len and Lerato, selecting suitable
transport projects, vary from being very basic to very complex. Consider the five scenarios (3.1-
3.5) regarding project selection models and answer in each case the following two questions (a
& b).
a) Identify the relevant scoring model suitable for project selection.
b) Classify the identified model as a numeric or non-numeric model.
Scenarios:
3.1 Len and Lerato can use this method when benefits of projects considered need to be
evaluated. It is therefore used when more than one project seems attractive to perform but
decisions must be made to select the one or two that would most benefit the organisation.
3.2. Len and Lerato can use this method for judging a new project to develop and distribute new
products on the degree to which it fits the organisation's existing product line, fills a gap,
strengthens a weak line, or extends the line in a new desirable direction.
3.3 Len and Lerato can use this method as it focuses on the value of the interest rate when
selecting a project and determines the interest rate required to make the present value of
the cash flows in the project equal to zero.
3.4 Len and Lerato can use this method when a project is perceived to be holy in the sense that
it has the personal support of part or all of top management and will be maintained until
successfully concluded.
3.5 Len and Lerato can use this method if the project is required in order to keep the system
operating, as long as the cost of the project is worth saving the system.
Clearly structure your answer using the following table template to answer the question.
QUESTION 4
Consider the following information to calculate the relevant values needed to answer the following
questions based on a network diagram for project XYZ. Only answer the questions.
 QUESTION 3 The scoring models used by two transport project managers,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!