Question: Question 3 : Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost

Question 3: Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost for the project is $700 and there is a savings of $50 per time unit reduced. Record the total direct, indirect, and project costs for each duration. What is the optimum cost-time schedule for the project? What is the cost?
Note: The correct normal project duration and total direct cost are provided. Show ALL of your working to get the points (15 bonus pts)
\table[[,\table[[Crash Cost],[(Slope)]],\table[[Maximum],[Crash Time]],\table[[Normal],[Time]],\table[[Normal],[Cost]]],[A,,0,2,100],[B,100,1,3,200],[C,40,1,5,200],[D,60,2,3,200],[E,20,1,5,200],[F,40,1,4,150],[G,,0,2,150]]
 Question 3: Use the information contained below to compress one time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!