Question: Question 2 : Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost

Question 2: Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost for the project is \(\$ 2,000\) and there is a savings of \(\$ 100\) per time unit reduced. Calculate the total direct, indirect, and project costs for each duration. What is the optimum cost-time schedule for the project?
Note: The correct normal project duration and total direct cost are provided. Show ALL of your working to get the points (30 pts ).
\begin{tabular}{ccccc}
\hline Act. & \begin{tabular}{c}
Crash Cost \\
(Slope)
\end{tabular} & \begin{tabular}{c}
Maximum \\
Crash Time
\end{tabular} & \begin{tabular}{c}
Normal \\
Time
\end{tabular} & \begin{tabular}{c}
Normal \\
Cost
\end{tabular}\\
\hline A & 0 & 2 & 200\\
B & 50 & 1 & 4 & 1000\\
C & 200 & 2 & 5 & 800\\
D & 200 & 2 & 5 & 1000\\
E & 100 & 1 & 3 & 800\\
F & 40 & 1 & 5 & 1000\\
G & 40 & 1 & 4 & 1000\\
H & & 0 & 1 & 200\\
\hline
\end{tabular}
\begin{tabular}{|ll|}
\hline & \\
\hline Project duration \(\underline{20}\)\\
\hline Direct cost & \(\underline{6,000}\)\\
Indirect cost & \(\underline{2,000}\)\\
\hline Total cost & \(\underline{8,000}\)\\
\hline
\end{tabular}
 Question 2: Use the information contained below to compress one time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!