Question 3 You are working on a project that has 12 activities and want to perform a PERT analysis on the project. You determine that the critical path consists of only five activities. You then compute the variances for the five critical activities and these variances are 3, 4, 2, 1, and 6 days. If the desired completion date for the project is 50 days, and the expected completion date for the project is 40 days, what is the probability that the project will not be more than the desired completion date