Question: QUESTION 30 Processing times and due dates for four jobs waiting to be processed at a work center are given in the following table. Determine

QUESTION 30

  1. Processing times and due dates for four jobs waiting to be processed at a work center are given in the following table. Determine the average flow time based on SPT rule.

    Job

    Processing time

    ( days)

    Due date

    (days)

    A 8 18
    B 6 13
    C 2 1
    D 4 8