Question: Question 31 (1 point) Listen The 100% Rule when applied to project management means that a) milestones have been effectively placed throughout the project and

Question 31 (1 point) Listen The "100% Rule" when

Question 31 (1 point) Listen The "100% Rule" when applied to project management means that a) milestones have been effectively placed throughout the project and all of the work in the project has been identified b) all of the work in the project has been identified c) no overallocation of resources exists d) all summary tasks have been included in the WBS e) milestones have been effectively placed throughout the project