Question: Question 14 (1 point) The 100% Rule when applied to project management means that a) milestones have been effectively placed throughout the project O b)
Question 14 (1 point) The "100% Rule" when applied to project management means that a) milestones have been effectively placed throughout the project O b) all of the work in the project has been identified c) milestones have been effectively placed throughout the project and all of the work in the project has been identified O d) all summary tasks have been included in the WBS O e) no overallocation of resources exists