Question: QUESTION 33 Processing times and due dates for four jobs waiting to be processed at a work center are given in the following table. Select

QUESTION 33

  1. Processing times and due dates for four jobs waiting to be processed at a work center are given in the following table. Select the correct choice

    Job

    Processing time

    ( days)

    Due date

    (days)

    A 8 18
    B 6 13
    C 2 1
    D 4 8

    MAKESPAN will be the same regardless of what rule (SPT, EDD, FCFS) is used in Scheduling

    MAKESPAN will NOT be the same regardless of what rule (SPT, EDD, FCFS) is used in Scheduling

    MAKESPAN is always NEGATIVE regardless of what rule (SPT, EDD, FCFS) is used in Scheduling

    None of them