Question: Question 35 (1 point) Under which circumstance would it be best to use a 3-point cost estimate when conducting Bottom-Up project cost planning? There is

Question 35 (1 point) Under which circumstance

Question 35 (1 point) Under which circumstance would it be best to use a 3-point cost estimate when conducting Bottom-Up project cost planning? There is limited time to undertake comprehensive detailed cost planning Due to work activity complexity it is difficult to obtain a defined cost estimate The work activity may have a range of possible successes The Subject Matter Expert (SME) has extensive costing experience in all project deliverables