Question: Under which circumstance would you not use a 3 - point cost estimate when conducting Top Down project cost planning? a . Work activity complexity

Under which circumstance would you not use a 3-point cost estimate when conducting Top Down project cost planning?
a. Work activity complexity makes it is important to obtain a defined cost estimate
b. The work activity may have a range of possible success outcomes
c. There is limited time to undertake comprehensive detailed cost planning
d. Top Down estimating only provides a rough high-level estimate
 Under which circumstance would you not use a 3-point cost estimate