Question: Question 35 (2.5 points) Saved Which statement is TRUE about Project Management? There can be more than one ways to draw the precedence graph, but

Question 35 (2.5 points) Saved Which statement is

Question 35 (2.5 points) Saved Which statement is TRUE about Project Management? There can be more than one ways to draw the precedence graph, but all precedence graphs must have an equal number of vertices. On a path that is not critical, all activities have a strictly positive slack. Project crashing always aims to minimize project duration subject to budget constraint. The earliest finish time of a task is equal to the sum of the latest start time of this task and the task duration. None of the above statements are true