Question: Question 37 (2 points) As discussed in the textbook, in a Kanban-based production control system the number of kanban card sets required must be calculated.

Question 37 (2 points) As discussed in the

Question 37 (2 points) As discussed in the textbook, in a Kanban-based production control system the number of kanban card sets required must be calculated. If expected demand during lead time = 50 per hour, safety stock is set at 20% of usage, container size = 4 units and the lead time to produce a batch = 8 hours, the correct value for the number of kanban card sets required is: (Hint: if necessary, round to nearest whole integer) D.L. (1+S) k= a) 60 Ob) 120 Oc) 150 Od 90 e) 80

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!