Question: Question 38 (1.5 points) If a project's PV is $200,000, and its EV is $175,000, then the project is ____? The project is $25,000 behind

Question 38 (1.5 points) If a project's PV is
Question 38 (1.5 points) If a project's PV is $200,000, and its EV is $175,000, then the project is ____? The project is $25,000 behind schedule The project is $25,000 ahead of schedule The project is on budget Not enough information is given