Question: Question 39 Which choice is definitely an incorrect suggestion on the subject of defining the work packages on a WBS? Not yet answered Marked out

Question 39 Which choice is definitely an

Question 39 Which choice is definitely an incorrect suggestion on the subject of defining the work packages on a WBS? Not yet answered Marked out of 1.00 O a. You must not have any WPs that duplicate parts of project scope Ob. Decompose the deliverables until you see the interrelationships between the activities required for their completion O c. It's OK if a few WPs contain most of project scope, as measured by cost Od Delivery of a single WP can be managed and controlled by one person Flag