Question: Question 3d (Uncheck every box to remove the question mark and then check all that apply.) If the project must be reduced by 3 days,

Question 3d (Uncheck every box to remove the

Question 3d (Uncheck every box to remove the question mark and then check all that apply.)

If the project must be reduced by 3 days, the activites most likely affected are

check all that apply

  • 1-2
  • 1-3
  • 1-4
  • 2-5
  • 2-6
  • 3-7
  • 4-7
  • 5-8
  • 6-8
  • 7-8
15 2 5 9 6 17 8 6 1 3 6 8 13 5 12 9 4 7 a) Determine Earliest Start time (ES), Earliest Finish time (EF), Latest Start time (LS), Latest Finish time (LF), and Slack Time for each activity. ES EF LS LF Slack Activity 1-2 1-3 1-4 2-5 2-6 3-7 4-7 5-8 6-8 7-8 b) Identify the Critical Path(s). c) What is the expected project duration? d) If the project duration must be reduced by 3 days, which activities will most likely be affected

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!