Question: Question 4 ( 1 . 5 0 points ) A project by Fernando Ferreira has an expected duration of 4 0 weeks and a variance
Question points
A project by Fernando Ferreira has an expected duration of weeks and a variance of weeks The project duration is assumed to be normally distributed.
a What is the probability of completing the project in weeks or less? point
b What is the probability of completing the project in weeks or less? point
c What duration would give Fernando a chance that the project is finished by that duration? point