Question: Activity Predecessors a m b A 2 5 8 B 6 7 8 C A 1 2 3 D A , B 6 7 8

Activity
Predecessors
a
m
b
A
2
5
8
B
6
7
8
C
A
1
2
3
D
A,B
6
7
8
E
C
2
5
8
F
C
1
2
9
G
D,E
4
5
12
H
F,G
2
3
4
From the table above find the flowing answers.
1. Construct the project Network
2. Find the expected duration and Variance of each activity
3. Find the critical path and expected project completion time
4. What is the probability of completion the project on or before 22 weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!