Question: Question 4 1 A task is d piecre of work that consumes time. Which staternent is false? 1 Gach activity defines how the work will
Question
A task is d piecre of work that consumes time. Which staternent is false?
Gach activity defines how the work will be done to produce a deliverable.
The duration of the activity is always equal to the total amount of work required to complete the deliverable.
As the project progresses the tasks are further defined and elaborated.
Tasks should be subdivided to a level where each task represents a deliverable for the project or the work package.