Question: Question 4 ( 1 point ) According to the CAT dozer production estimating method, the correction factor for a soil density of 1 9 5

Question 4(1 point)
According to the CAT dozer production estimating method, the correction factor for a soil density of 1950lbLCY is most nearly (refer to CAT Handbook 16-17):
1.18
0.75
1.00
0.85
Question 4 ( 1 point ) According to the CAT dozer