Question 4 (1 point) The project manager is allocating overall cost to individual activities to establish a time phased yardstick for measuring project performance. What process is this? a) Establishing the Cost Baseline b) Establishing Intent for Cost c) Plan Cost Management d) Establishing the Schedule Baseline e) Establishing the Scope Baseline