Question: Question 4 1 pts A future project has an uncertain finish time and the finish time follows a normal distribution. The project's expected finish time
Question 4 1 pts A future project has an uncertain finish time and the finish time follows a normal distribution. The project's expected finish time is 35 weeks, and the project variance is 9 weeks. If the project deadline is set to be 59 weeks, then what is the probability that the project would need more than the given deadline to complete? Input should be either 1 or 2. with 1 represents "more than 50%" and 2 represents "equal or less than 50%" 21
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
