Question: Question 4 1 pts Tinyfield Labs' first process is performed at a bottleneck station that has 5 identical machines working on a NON - batched

Question 4
1 pts
Tinyfield Labs' first process is performed at a bottleneck station that has 5 identical machines
working on a NON-batched process. A job can be taken by any one of the unoccupied machines
and needs to be processed by only one of the machines at this station. It takes a machine on
average 5 hours to process a job. The expected (average) daily demand is 18 jobs per day to arrive
at Tinyfield. What is the capacity utilizaton of this station?
75%
72%
28%
27%